http://www.kaieteurnewsonline.com/2012/09/19/amaila-falls-hydro-electric-projectus840m-price-tag-assured-sithe-global/
According to AFH yesterday, the hydro-power project reached major development milestones last week, with the signing of key project agreements in Xi’an, China, including the EPC contract and the Inter-American Development Bank Mandate Letter.
“This sets in motion the next phase of lender due diligence and documentation needed to reach project financial closure and begin construction, which is scheduled to start in the second quarter of 2013. The milestones demonstrate the hard work and commitment of all parties in making the project a reality for Guyana.”
The EPC contract is valued at US$506M.
“Signing the EPC contract provides price certainty, avoiding the risk of commodity price adjustments for a period of nine (9) months, during which AFH will secure the project financing. The pricing is subject to adjustment in currency fluctuation until financial closure is reached, at which time the pricing will be fixed.”
According to AFH, Sithe Global will lead the oversight of the construction activity, using its core management team which has “successfully led the development or acquisition of over 70 power plants comprising more than 18,000 megawatts globally. China Railway, one of the world’s largest infrastructure construction companies with significant experience building hydropower plants, will build the power facility and transmission lines.”
Traductor Google
Tomado
de:
Amaila
Falls proyecto hidroeléctrico ... EE.UU. $ 840M
Precio
asegurado - Sithe Global
19 de
septiembre 2012 | Por knews | Archivado en Noticias
- Cierre financiero dentro de los nueve meses, inmediatamente después de la construcción
- Cierre financiero dentro de los nueve meses, inmediatamente después de la construcción
El
cierre financiero para la masiva EE.UU. $ 840M Amaila Falls hidroeléctrica
proyecto se prevé un plazo de nueve meses con la construcción configurado para
iniciarse poco después, los desarrolladores divulgada ayer.
El
Amaila Falls Hydro Inc. (AFH), la compañía operadora local formada para
administrar el proyecto 165-megawatt que se encuentra en la Región Ocho,
también indicó que los caminos de acceso al sitio tendrá que ser completado
antes de que comience la construcción
Los
caminos se enfrentan a importantes retrasos después de que el primer
contratista, Synergy Holdings Inc., no cumplió con los plazos y los contratos
se rompieron en enero por el gobierno y la adjudicación fraccionada a varias
empresas de construcción.
"AFH
espera que el cierre financiero en el segundo trimestre de 2013, con el inicio
de la construcción inmediatamente después de eso (el proyecto de la carretera
de acceso debe ser completado antes de comenzar la construcción del
proyecto)".
La
compañía dijo que entregará energía hidroeléctrica en tres años y medio y o 42
meses.
El
proyecto hidroeléctrico, la inversión más grande en la historia de Guyana, se
ha visto afectado con las cuestiones de costos, retrasos en el acceso de
construcción de carreteras y la aptitud de los contratistas.
Había
muchas preguntas cuando los contratos fueron adjudicados a la carretera
Synergy, pero el gobierno había salido mucho en la defensa de la capital,
Motilall 'Fip' Makeshwar, para quien no se haya podido evidencia inmediata o
experiencia de construcción de carreteras encontrado.
La
semana pasada, el gobierno anunció que Sithe Global, los desarrolladores, había
firmado un Ingeniería, Procura y Construcción (EPC) el acuerdo con China
Railway First Group (CRFG).
Hubo
preguntas inmediatas sobre la idoneidad de que la empresa china después de
reportes de la prensa reveló que el año pasado Polonia había roto un proyecto
de varios millones de dólares con una de las filiales en el extranjero, debido
a problemas de liquidez experimentadas por dicha empresa. La firma china
presuntamente exigió más dinero para completar el proyecto de la carretera, pero
se negó el gobierno polaco.
También
hubo declaraciones a principios de este mes que el gobierno paquistaní se negó
a dar luz verde a un proyecto ferroviario y en su lugar comenzó una
investigación para determinar la forma en que se adjudicó el contrato en el
primer lugar.
No hay
ajustes de precios
De
acuerdo con AFH ayer, el proyecto hidroeléctrico alcanzado importantes logros
en el desarrollo la semana pasada, con la firma de los acuerdos de proyectos
clave en Xi'an, China, incluido el contrato EPC y la Carta de Desarrollo del
Banco Interamericano de Mandato.
"Esto pone en marcha la siguiente fase de diligencia debida prestamista y documentación necesaria para alcanzar el cierre financiero del proyecto y comenzar la construcción, que está programada para comenzar en el segundo trimestre de 2013. Los hitos demuestran el trabajo duro y el compromiso de todas las partes en que el proyecto sea una realidad para Guyana ".
"Esto pone en marcha la siguiente fase de diligencia debida prestamista y documentación necesaria para alcanzar el cierre financiero del proyecto y comenzar la construcción, que está programada para comenzar en el segundo trimestre de 2013. Los hitos demuestran el trabajo duro y el compromiso de todas las partes en que el proyecto sea una realidad para Guyana ".
El
contrato EPC tiene un valor de EE.UU. $ 506 millones.
"La firma del contrato EPC proporciona certeza precio, evitando el riesgo de que los ajustes de precios de los productos básicos por un período de nueve (9) meses, durante los cuales AFH asegurar la financiación del proyecto. El precio está sujeto a ajustes en la fluctuación de la moneda hasta el cierre financiero se alcance, momento en el cual el precio será fijo. "
"La firma del contrato EPC proporciona certeza precio, evitando el riesgo de que los ajustes de precios de los productos básicos por un período de nueve (9) meses, durante los cuales AFH asegurar la financiación del proyecto. El precio está sujeto a ajustes en la fluctuación de la moneda hasta el cierre financiero se alcance, momento en el cual el precio será fijo. "
De
acuerdo con AFH, Sithe Global conducirá la supervisión de la actividad de la
construcción, el uso de su equipo de gestión central que ha "liderado con
éxito el desarrollo o la adquisición de más de 70 plantas de energía con más de
18.000 megavatios a nivel mundial. China Railway, una de las mayores empresas
constructoras de infraestructuras del mundo con plantas hidroeléctricas
importantes experiencias de construcción, construirá la planta de energía y
líneas de transmisión. "
Contrato
de robusta
AFC
insistió ayer en que los "requisitos firmes contractuales del contrato EPC
exige que la fuerza, la estructura y la integridad de la presa y la
infraestructura asociada planta de energía será de normas internacionales
aceptadas".
Sithe Global seguirá de cerca la aplicación y garantizar el estricto cumplimiento de las normas.
Sithe Global seguirá de cerca la aplicación y garantizar el estricto cumplimiento de las normas.
"La
supervisión adicional tercera parte se llevará a cabo por el ingeniero de la
entidad crediticia, ingeniero del propietario (MWH, uno de los más grandes
ingenieros hidráulicos en los EE.UU.), así como un panel independiente de
expertos en seguridad de presas y represas."
La compañía dijo que la firma de la Carta de Mandato entre el BID y AFH representa una pieza fundamental del sistema de financiación del proyecto.
La compañía dijo que la firma de la Carta de Mandato entre el BID y AFH representa una pieza fundamental del sistema de financiación del proyecto.
"Este
importante avance permite a los prestamistas del proyecto (BID y el Banco de
Desarrollo de China) para continuar con la fase final de la diligencia debida y
la redacción de la documentación necesaria financiación. AFH y prestamistas del
proyecto están trabajando duro para finalizar los arreglos de financiación
mientras empuja la tarifa más baja posible ".
Gobierno
ha dicho que el proyecto reducirá la dependencia de Guyana de los combustibles
fósiles importados, que es la principal fuente de energía.
AFH es
un miembro del grupo de Sithe Global, constituida en Guyana con el fin de
desarrollar, poseer y operar la Amaila Falls proyecto hidroeléctrico.
AFH
dijo que ha gastado más de EE.UU. $ 11M en tercero los costes medioambientales,
técnicos y jurídicos relacionados con el desarrollo y la financiación del
proyecto.
"AFH tiene la intención de contribuir en más de EE.UU. $ 120 millones de fondos propios durante el período de construcción.
"AFH tiene la intención de contribuir en más de EE.UU. $ 120 millones de fondos propios durante el período de construcción.
Sithe
Global accionista mayoritario, el Grupo Blackstone, se dice que es gerente de
uno de los mayores fondos de capital privado del mundo, con activos totales
bajo gestión de aproximadamente EE.UU. $ 190B al 30 de junio de 2012
Amaila Falls
Hydro-Electric Project…US$840M price tag assured – Sithe Global
- financial
closure within nine months, construction immediately after
Financial
closure for the massive US$840M Amaila Falls hydro electric project is expected
within nine months with construction set to start shortly after, the developers
disclosed yesterday.
The Amaila Falls Hydro Inc. (AFH), the local operating company formed to manage the 165-megawatt project to be situated in Region Eight, also indicated that the access roads leading to the site will have to be completed before construction begins.
The roads were faced with major delays after the first contractor, Synergy Holdings Inc., failed to meet deadlines and the contracts were severed in January by government and awarded in parts to several other construction firms.
“AFH expects financial closure in the second quarter of 2013, with construction beginning immediately thereafter (the Access Road Project is to be completed prior to commencing construction of the Project).”
The company said that it will deliver hydro energy in three and half years or 42 months.
The hydro project, the largest single investment in Guyana’s history, has been marred with questions of cost, access road construction delays and the suitability of contractors.
There were numerous questions when the road contracts were awarded to Synergy, but government had come out heavily in defense of the principal, Makeshwar ‘Fip’ Motilall, for whom no immediate evidence or road building experience could be found.
Last week, government announced that Sithe Global, the developers, had signed an Engineering, Procurement & Construction (EPC) agreement with China Railway First Group (CRFG).
There were immediate questions about the suitability of that Chinese firm after media reports revealed that last year Poland had severed a multi-million-dollar project with one of the overseas subsidiaries because of cash problems experienced by that company. The Chinese firm reportedly demanded more money to complete the highway project, but the Polish government refused.
There were also disclosures earlier this month that the Pakistani government refused to green-light a railway project and instead started an investigation to determine how it was awarded the contract in the first place.
The Amaila Falls Hydro Inc. (AFH), the local operating company formed to manage the 165-megawatt project to be situated in Region Eight, also indicated that the access roads leading to the site will have to be completed before construction begins.
The roads were faced with major delays after the first contractor, Synergy Holdings Inc., failed to meet deadlines and the contracts were severed in January by government and awarded in parts to several other construction firms.
“AFH expects financial closure in the second quarter of 2013, with construction beginning immediately thereafter (the Access Road Project is to be completed prior to commencing construction of the Project).”
The company said that it will deliver hydro energy in three and half years or 42 months.
The hydro project, the largest single investment in Guyana’s history, has been marred with questions of cost, access road construction delays and the suitability of contractors.
There were numerous questions when the road contracts were awarded to Synergy, but government had come out heavily in defense of the principal, Makeshwar ‘Fip’ Motilall, for whom no immediate evidence or road building experience could be found.
Last week, government announced that Sithe Global, the developers, had signed an Engineering, Procurement & Construction (EPC) agreement with China Railway First Group (CRFG).
There were immediate questions about the suitability of that Chinese firm after media reports revealed that last year Poland had severed a multi-million-dollar project with one of the overseas subsidiaries because of cash problems experienced by that company. The Chinese firm reportedly demanded more money to complete the highway project, but the Polish government refused.
There were also disclosures earlier this month that the Pakistani government refused to green-light a railway project and instead started an investigation to determine how it was awarded the contract in the first place.
No price
adjustments
According to AFH yesterday, the hydro-power project reached major development milestones last week, with the signing of key project agreements in Xi’an, China, including the EPC contract and the Inter-American Development Bank Mandate Letter.
“This sets in motion the next phase of lender due diligence and documentation needed to reach project financial closure and begin construction, which is scheduled to start in the second quarter of 2013. The milestones demonstrate the hard work and commitment of all parties in making the project a reality for Guyana.”
The EPC contract is valued at US$506M.
“Signing the EPC contract provides price certainty, avoiding the risk of commodity price adjustments for a period of nine (9) months, during which AFH will secure the project financing. The pricing is subject to adjustment in currency fluctuation until financial closure is reached, at which time the pricing will be fixed.”
According to AFH, Sithe Global will lead the oversight of the construction activity, using its core management team which has “successfully led the development or acquisition of over 70 power plants comprising more than 18,000 megawatts globally. China Railway, one of the world’s largest infrastructure construction companies with significant experience building hydropower plants, will build the power facility and transmission lines.”
Robust
contract
AFC insisted yesterday that the “robust contractual requirements of the EPC contract require that the strength, structure and integrity of the dam and associated power plant infrastructure will be of accepted international standards”.
Sithe Global will closely monitor the implementation and ensure strict compliance with the standards.
“Further third party oversight will be conducted by the lender’s engineer, the owner’s engineer (MWH, one of the largest hydro engineers in the USA), as well as an independent panel of experts in dams and dam safety.”
The company said that the signing of the Mandate Letter between the IDB and AFH represents a critical piece of the project financing scheme.
“This significant step forward allows the lenders of the Project (IDB and China Development Bank) to proceed with the final phase of due diligence and draft the required financing documentation. AFH and Project lenders are working hard to finish the financing arrangements while pushing the tariff as low as possible.”
Government has said that the project will reduce Guyana’s dependence on imported fossil fuel which is the main source of energy.
AFH is a member of the Sithe Global group, incorporated in Guyana for the purpose of developing, owning and operating the Amaila Falls Hydropower Project.
AFH said that it has spent over US$11M on third party environmental, technical and legal costs associated with the development and financing of the project.
“AFH intends to contribute in excess of US$120 million of equity funding during the construction period.
Sithe Global’s majority shareholder, the Blackstone Group, is said to be manager of one of the largest private equity funds in the world with total assets under management of approximately US$190B as of June 30, 2012.
AFC insisted yesterday that the “robust contractual requirements of the EPC contract require that the strength, structure and integrity of the dam and associated power plant infrastructure will be of accepted international standards”.
Sithe Global will closely monitor the implementation and ensure strict compliance with the standards.
“Further third party oversight will be conducted by the lender’s engineer, the owner’s engineer (MWH, one of the largest hydro engineers in the USA), as well as an independent panel of experts in dams and dam safety.”
The company said that the signing of the Mandate Letter between the IDB and AFH represents a critical piece of the project financing scheme.
“This significant step forward allows the lenders of the Project (IDB and China Development Bank) to proceed with the final phase of due diligence and draft the required financing documentation. AFH and Project lenders are working hard to finish the financing arrangements while pushing the tariff as low as possible.”
Government has said that the project will reduce Guyana’s dependence on imported fossil fuel which is the main source of energy.
AFH is a member of the Sithe Global group, incorporated in Guyana for the purpose of developing, owning and operating the Amaila Falls Hydropower Project.
AFH said that it has spent over US$11M on third party environmental, technical and legal costs associated with the development and financing of the project.
“AFH intends to contribute in excess of US$120 million of equity funding during the construction period.
Sithe Global’s majority shareholder, the Blackstone Group, is said to be manager of one of the largest private equity funds in the world with total assets under management of approximately US$190B as of June 30, 2012.
1994
Guayana Esequiba - Zona en Reclamación MARNR Servicio Autónomo de
Geografía y Cartografía Nacional 3 Edición
Nota
del editor del blog: Al referenciarse a la
República Cooperativa de Guyana se deben de tener en cuenta los 159.500Km2, de
territorios ubicados al oeste del río Esequibo conocidos con el nombre de
Guayana Esequiba o Zona en Reclamación sujetos al Acuerdo de Ginebra del 17 de
febrero de 1966.
Territorios estos sobre los cuales el gobierno
Venezolano en representación de la Nación venezolana se reservo sus derechos
sobre los territorios de la Guayana Esequiba en su nota del 26 de mayo de 1966
al reconocerse al nuevo Estado de Guyana .
“...por lo tanto, Venezuela reconoce como territorio
del nuevo Estado, el que se sitúa al este de la margen derecha del río Esequibo
y reitera ante la comunidad internacional, que se reserva expresamente sus
derechos de soberanía territorial sobre la zona que se encuentra en la margen
izquierda del precitado río; en consecuencia, el territorio de la Guayana
Esequiba sobre el cual Venezuela se reserva expresamente sus derechos
soberanos, limita al Este con el nuevo Estado de Guyana, a través de la línea
del río Esequibo, tomando éste desde su nacimiento hasta su desembocadura en el
Océano Atlántico...”
Mapa que señala el Espacio
de Soberanía Marítima Venezolana que se reserva, como Mar Territorial mediante el Decreto
Presidencial No 1152 del 09 de Julio de 1968.
No hay comentarios:
Publicar un comentario