domingo, 17 de junio de 2012

EL Proyecto hidroeléctrico de Amaila actualización (Zona en Reclamación Guayana Esequiba)

http://www.stabroeknews.com/2012/opinion/letters/06/17/hopeful-that-amaila-falls-hydro-project-will-start-final-due-diligence-documentation-in-july/


Tomado de:
Traducción Google:
La esperanza de que Amaila Falls proyecto hidroeléctrico comenzará final de la diligencia debida documentación, en julio


Publicado por Stabroek personal en 17 de junio 2012 @ 05:02 am En Cartas
 |
Sr. Director:

Amaila Falls Hydro Inc (AFH) aprovecha esta oportunidad para ofrecer a la siguiente actualización sobre el Proyecto Hidroeléctrico Amaila (Proyecto). Agradecemos el interés público continua, para mantener líneas de comunicación transparentes con respecto al proyecto.

Durante nuestras reuniones en Guyana a principios de este año, funcionarios de Sithe Global ofrece una mirada detallada en los costos del proyecto, los plazos y las cuestiones que llevaron al cierre financiero del proyecto.En ese momento, estábamos esperando una aprobación por los prestamistas para que un cierre financiero para este verano. Mientras que el tiempo se ha deslizado, nuestros prestamistas siguen siendo favorables del proyecto.

Hemos trabajado estrechamente con el Banco Interamericano de Desarrollo (BID) para hacer frente a su preocupación por Guyana Power and Light de (GPL) la capacidad técnica y financiera. Sobre la base de nuestras conversaciones con el BID, tenemos la esperanza de que el proyecto se borrará para iniciar diligencias y la documentación en julio.

El cierre financiero del proyecto debe ocurrir 6-8 meses después. Este retraso es una decepción para nosotros, pero reconocemos que los proyectos de transformación de esta naturaleza requiere una cuidadosa planificación para asegurar una implementación exitosa.

Uno de los riesgos de la demora es que el precio del contrato de construcción del proyecto podría aumentar.

Estos aumentos podrían deberse a cambios en los tipos de cambio u otros factores. Mientras que los ajustes anteriores de divisas como resultado un aumento sustancial de los costes, el dólar de EE.UU. a Yuan Chino Renminbi tasas de cambio de divisas no se han movido significativamente en el primer semestre de 2012.

Sin embargo, es imposible predecir los cambios futuros en las tasas de cambio u otros factores, lo que significa que el riesgo de aumento de los precios sigue siendo un problema grave hasta que se logre el cierre financiero.
Seguimos trabajando diligentemente para mantener la estructura actual de precios de la construcción y mantenimiento de la viabilidad del proyecto en medio de las demoras en la obtención de la deuda del proyecto de nuestros prestamistas.

El proyecto se mantiene fundamentalmente fuerte debido a que es la opción de menor costo para la licencia GPL y sus contribuyentes.

Sigue representan lo mejor de bajo costo, a largo plazo de la opción de reducir los costos promedio de generación de GPL y la dependencia de los combustibles fósiles importados. Por otra parte, implica una mejora significativa de la infraestructura eléctrica en Guyana que apoye el crecimiento económico general de Guyana y el desarrollo sostenible, basado en una fuente limpia, electricidad confiable y asequible para sus industrias, comercios y residentes. Sithe Global espera asociarse con el pueblo de Guyana en este emocionante proyecto.

Le saluda atentamente,

Brian Kubeck

Bruce Wrobel

Artículo original de Stabroek News:

URL del artículo:
Deshacer cambios


Hopeful that Amaila Falls Hydro project will start final due diligence, documentation in July


Posted By Stabroek staff On June 17, 2012 @ 5:02 am In Letters |
Dear Editor,
Amaila Falls Hydro Inc (AFH) takes this opportunity to offer the following update regarding the Amaila Hydropower Project (Project). We appreciate the continued public interest as we maintain transparent lines of communication regarding the Project.

During our meetings in Guyana earlier this year, Sithe Global officials offered a detailed look into the project costs, timelines and issues leading up to the financial closure of the project.

At the time, we were anticipating an approval by lenders to enable a financial closure by this summer. While that timing has slipped, our lenders remain supportive of the project.

We have worked closely with the Inter-American Development Bank (IDB) to address its concern about Guyana Power and Light’s (GPL) technical and financial capacity. Based on our discussions with IDB, we are hopeful that the project will be cleared to start final due diligence and documentation in July.

The project’s financial closure should occur 6-8 months thereafter. This delay is a disappointment to us, but we recognize that transformational projects of this nature require careful advance planning to ensure successful implementation.

One risk of delay is that the project’s construction contract price could increase. Such increases could result from changes in foreign currency exchange rates or other factors. While previous currency adjustments resulted in substantial cost increases, the US dollar to Chinese yuan renminbi foreign exchange rates have not moved significantly in the first half of 2012.

However, it is impossible to predict future changes in currency rates or other factors, meaning that the risk of price increases remains a serious concern until we achieve financial closing.

We continue to work diligently to maintain the current construction pricing structure and maintain the viability of the project amidst the delays in securing the project debt from our lenders.

The project remains fundamentally strong because it is the lowest cost option for GPL and its ratepayers.

It continues to represent the best low-cost, long-term option to reduce GPL’s average generation costs and dependency on imported fossil fuels. Furthermore, it entails a significant improvement of the electricity infrastructure in Guyana that will support Guyana’s overall economic growth and sustainable development, based on a clean, reliable and affordable electricity supply for its industries, businesses and residents. Sithe Global looks forward to partnering with the people of Guyana on this exciting project.

Yours faithfully,
Brian Kubeck
Bruce Wrobel

Article printed from Stabroek News:
http://www.stabroeknews.com
URL to article:
1994 Guayana Esequiba - Zona en Reclamación MARNR Servicio Autónomo  de Geografía y Cartografía Nacional 3 Edición

Nota del editor del blog: Al referenciarse a la República Cooperativa de Guyana se deben de tener en cuenta los 159.500Km2, de territorios ubicados al oeste del río Esequibo conocidos con el nombre de Guayana Esequiba o Zona en Reclamación sujetos al Acuerdo de Ginebra del 17 de febrero de 1966.

Territorios estos sobre los cuales el gobierno Venezolano en representación de la Nación venezolana se reservo sus derechos sobre los territorios de la Guayana Esequiba en su nota del 26 de mayo de 1966 al reconocerse al nuevo Estado de Guyana .
“...por lo tanto, Venezuela reconoce como territorio del nuevo Estado, el que se sitúa al este de la margen derecha del río Esequibo y reitera ante la comunidad internacional, que se reserva expresamente sus derechos de soberanía territorial sobre la zona que se encuentra en la margen izquierda del precitado río; en consecuencia, el territorio de la Guayana Esequiba sobre el cual Venezuela se reserva expresamente sus derechos soberanos, limita al Este con el nuevo Estado de Guyana, a través de la línea del río Esequibo, tomando éste desde su nacimiento hasta su desembocadura en el Océano Atlántico...”


 Mapa que señala el Espacio de Soberanía Marítima Venezolana que se reserva, como Mar Territorial mediante el Decreto Presidencial No 1152 del 09 de Julio de 1968.

No hay comentarios: