Optimismo cauteloso para
la realización de Amaila acceso Falls Road
Tomado de:
Optimismo cauteloso para
la realización de Amaila acceso Falls Road
Traducción Google
Ingeniero
Toolsie Persaud Canteras 'Romeo Ramascindo, con la ayuda de un mapa, explica
trabaja llevando a cabo a lo largo del río Kuribrong, en la que el Amaila Falls
proyecto hidroeléctrico de energía se construirá.
Escrito por
Lunes, 26 de marzo 2012 22:08
- La restricción de los
retos futuros de mayo / junio de lluvias
Una visita a la carretera de acceso
Amaila Cataratas el fin de semana permitió a un equipo de funcionarios para
evaluar los trabajos que está realizando nuevos contratistas, dos meses después
de la terminación del contrato celebrado por la FIP Motilall y Synergy Holdings
Ltd. El presidente Donald Ramotar, Ministro de Obras
Públicas, Robeson Benn, y el consultor de ingeniería para el Gobierno Walter
Willis encabezó el equipo que visitó varias secciones de los más de 80
kilómetros de carretera que ha de llevarse a cabo antes de comenzar el trabajo
sobre el proyecto de energía hidroeléctrica. La
Primera Dama Deolatchmee Ramotar también acompañó al equipo.
El Amaila Falls proyecto hidroeléctrico está siendo vigorosamente por la Administración sobre la base de que reduciría significativamente EE.UU. $ 350 millones de Guyana factura de las importaciones de combustible, y reducir al mínimo el impacto del movimiento del precio del combustible en el costo de la generación de energía. El desarrollo de fuentes renovables de energía es necesaria para aumentar la seguridad energética y mantener la estabilidad macroeconómica.
El proyecto, que tiene la capacidad de ofrecer más de 140 megavatios de electricidad, es que se encuentra junto al río Kuribrong en Potaro, Región 8.
Presidente Ramotar declaró que estaba satisfecho con el trabajo que se realiza en las secciones tres y cuatro, a pesar de que reconoce que no habrá problemas para completarlo.
"Los trabajadores y la dirección de la me han asegurado que ellos pueden hacerlo", dijo. "Ellos están más preocupados ahora de las lluvias de mayo / junio ... Me gusta el espíritu, son optimistas y parece preparado para el desafío de tratar de conseguir este camino completado por lo que vamos a ser capaces de obtener energía hidroeléctrica de nuestro país".
Ministro Benn dijo: "Hemos sido capaces de reiniciar tres secciones ... que prohíben a los desafíos del clima, contratistas, consultores, ingenieros, trabajadores del Ministerio ... están preparadas y preparados para cumplir con esta labor, antes de la construcción de la represa hidroeléctrica , ", dijo.
Desde contrato de 15,4 millones de dólares EE.UU.
Motilall se dio por terminado, por el
incumplimiento de uno de los términos de un acuerdo de terminación, Toolsie
Persaud Canteras Inc. se adjudicó el contrato para construir la unión
Kurupukari y también tiene el contrato para la sección cuatro. El proyecto, que ahora
se ejecuta en lotes, podrá ver otros contratistas reclutados.
La quinta sección se ha asignado a Ivor Allen, mientras que las secciones seis y siete están pendientes de asignar. Las ofertas están fuera de la última sección.
Willis dijo que los contratistas desea reiniciar el trabajo en la sección dos, utilizando los recursos del anterior contrato de Amaila Falls, junto con los recursos adicionales del Ministerio de Obras Públicas.
Contratista Toolsie Persaud Canteras ', Romeo Ramascindo, señaló que el río Kuribrong se ha despejado, mientras que un pantano de alto nivel en la segunda sección se ha excavado, se llena y camas. "Ahora se puede subir a unos dos kilómetros antes del río Kuribrong", dijo el presidente Ramotar.
En el trato con los pantanos se encuentran, explicó que las alcantarillas se va a excavar y el aumento de los terraplenes se construirá por encima de su planicie de inundación. Las tuberías de drenaje intermitentes se instalará y los puentes colocados en medio de los pantanos. El exceso de agua bajando por los lados del terraplén se ejecutará a través de los carriles del puente. Además, para proteger los muros de contención, la tela y rocas de laterita se colocará.
El Proyecto Amaila implica la construcción de una planta hidroeléctrica en el área de centro-oeste de Guyana, donde los ríos y Amaila Kuribrong cumplir. La electricidad producida en la planta será entregada a Georgetown y Linden a través de una alta tensión de 230 kV de la línea de transmisión que se construirá, junto con subestaciones eléctricas en Linden y Georgetown.
Una nueva carretera, a unos 65 kilómetros de longitud, se construirá la conexión al sitio del proyecto a la existente Bartica Potaro-Road. Otra nueva carretera, a unos 20 km, se construye a partir de la actual carretera Mabura Hills hasta el río Esequibo. Otras carreteras existentes se actualizarán a fin de proporcionar el acceso necesario para mover el equipo, suministros y personal para construir el proyecto, así como para su posterior operación y mantenimiento de la planta y líneas de transmisión.
Cautious optimism for completion of Amaila Falls
access road
Toolsie Persaud Quarries’ Engineer Romeo Ramascindo,
with the aid of a map,explains works being done along the Kuribrong River, on
which the Amaila Falls Hydro power project will be built
Tomado de:
Written by
Monday, 26 March 2012 22:08
– barring challenges of upcoming May/June rains
A SITE visit to the Amaila Falls access road over the weekend enabled a team of officials to assess the works being done by new contractors, two months after the termination of the contract held by Fip Motilall and Synergy Holdings Ltd.
A SITE visit to the Amaila Falls access road over the weekend enabled a team of officials to assess the works being done by new contractors, two months after the termination of the contract held by Fip Motilall and Synergy Holdings Ltd.
Toolsie Persaud Quarries’ Engineer Romeo Ramascindo,
with the aid of a map,explains works being done along the Kuribrong River, on
which the Amaila Falls Hydro power project will be built.
President Donald Ramotar, Minister of Public Works
Robeson Benn, and Engineering Consultant to the Government Walter Willis headed
the team which visited several sections of the more than 80 kilometres of roadway
that has to be completed before work commences on the hydro power project.
First Lady Deolatchmee Ramotar also accompanied the team.
The Amaila Falls Hydropower project is being
vigorously pursued by the Administration on the basis that it would significantly
reduce Guyana’s US$350M fuel import bill, and minimise the impact of fuel price
movement on the cost of generating power. The development of renewable energy
sources is needed to increase energy security and maintain macro-economic
stability.
The project, which has the capacity to provide over
140 megawatts of electricity, is to be located along the Kuribrong River in
Potaro, Region 8.
President Ramotar stated that he was pleased with the
work being done in sections three and four, even though he recognises that
there will be challenges to complete it.
“The workers and the management have assured me that they can do it,” he said. “They are more worried now about the May/June rains…I like the spirit, they are optimistic and they seem up to the challenge to try to get this road completed so that we will be able to get hydro electricity for our country.”
“The workers and the management have assured me that they can do it,” he said. “They are more worried now about the May/June rains…I like the spirit, they are optimistic and they seem up to the challenge to try to get this road completed so that we will be able to get hydro electricity for our country.”
Minister Benn said, “We have been able to restart
three sections …barring the challenges of weather; contractors, consultants,
workers, engineers at the Ministry…are geared up and prepared to get this job
done, before the construction of the hydro power dam,” he said.
Since Motilall’s US$15.4M contract was terminated, for
failure to honour one of the terms of a completion agreement, Toolsie Persaud
Quarries Inc. was awarded the contract to build the Kurupukari junction and it
also holds the contract for section four. The project, which will now be
executed in lots, will see other contractors being recruited.
Section five has been allocated to Ivor Allen, while sections six and seven are yet to be allocated. Bids are out for the latter section.
Section five has been allocated to Ivor Allen, while sections six and seven are yet to be allocated. Bids are out for the latter section.
Willis said that the contractors want to restart work
at section two, using resources from the previous Amaila Falls contract, along
with additional resources from the Ministry of Public Works.
Toolsie Persaud Quarries’ contractor, Romeo
Ramascindo, noted that the Kuribrong River has been cleared while a high level
swamp in section two has been dug out, filled and bedded. “You can now drive up
to about two kilometres before the Kuribrong River,” he told President Ramotar.
In dealing with swamps encountered, he explained that
culverts will be dug and higher embankments will be built above their
floodplain. Intermittent drainage pipes will then be installed and bridges
placed in between the swamps. Excess water going down the sides of the
embankment will run through the bridge lanes. Additionally, to protect the
embankments, fabric and laterite boulders will be placed.
The Amaila Project involves the construction of a hydropower plant in the area of west-central Guyana, where the Amaila and Kuribrong rivers meet. Electricity produced at the plant will be delivered to Georgetown and Linden through a high-voltage 230-KV transmission line that will be built, along with electric substations in Linden and Georgetown.
The Amaila Project involves the construction of a hydropower plant in the area of west-central Guyana, where the Amaila and Kuribrong rivers meet. Electricity produced at the plant will be delivered to Georgetown and Linden through a high-voltage 230-KV transmission line that will be built, along with electric substations in Linden and Georgetown.
A new road, approximately 65 kms long, will be built
connecting the project site to the existing Bartica-Potaro Road. Another new
road, approximately 20 km, will be constructed from the existing Mabura Hills
Highway to the Essequibo River. Other existing roads will be upgraded in order
to provide access needed to move the equipment, supplies, and personnel to
build the project, as well as for future operation and maintenance of the plant
and transmission lines.
1994 Guayana
Esequiba - Zona en Reclamación MARNR Servicio Autónomo de Geografía y Cartografía Nacional 3 Edición
Nota del editor del blog: Al
referenciarse a la República Cooperativa de Guyana se deben de tener en cuenta
los 159.500Km2, de territorios ubicados al oeste del río Esequibo conocidos con
el nombre de Guayana Esequiba o Zona en Reclamación sujetos al Acuerdo de
Ginebra del 17 de febrero de 1966.
Territorios estos sobre los cuales el
gobierno Venezolano en representación de la Nación venezolana se reservo sus
derechos sobre los territorios de la Guayana Esequiba en su nota del 26 de mayo
de 1966 al reconocerse al nuevo Estado de Guyana .
“...por lo tanto, Venezuela reconoce
como territorio del nuevo Estado, el que se sitúa al este de la margen derecha
del río Esequibo y reitera ante la comunidad internacional, que se reserva
expresamente sus derechos de soberanía territorial sobre la zona que se
encuentra en la margen izquierda del precitado río; en consecuencia, el
territorio de la Guayana Esequiba sobre el cual Venezuela se reserva
expresamente sus derechos soberanos, limita al Este con el nuevo Estado de Guyana,
a través de la línea del río Esequibo, tomando éste desde su nacimiento hasta
su desembocadura en el Océano Atlántico...”
No hay comentarios:
Publicar un comentario