lunes, 3 de diciembre de 2012

Los contratistas del proyecto Amaila están a la altura y resolverán el problema de la carretera (La Guayana Esequiba-Zona en Reclamación)


http://www.guyanachronicleonline.com/site/index.php?option=com_content&view=article&id=52453:contractors-who-fall-short-on-amaila-falls-road-project-to-be-reassessed-pm-hinds-&catid=4:top-story&Itemid=8http://www.guyanachronicleonline.com/site/index.php?option=com_content&view=article&id=52453:contractors-who-fall-short-on-amaila-falls-road-project-to-be-reassessed-pm-hinds-&catid=4:top-story&Itemid=8

Traductor Google:

Contratistas que están a la altura en el proyecto Amaila

Carretera Falls ser reevaluado - PM Hinds

Tomado de:

Contratistas que están a la altura en el proyecto Amaila carretera Falls ser reevaluado - PM Hinds
Domingo, 02 de diciembre 2012 20:03

El primer ministro Samuel Hinds dijo que una re-evaluación se fija para comenzar en breve con los contratistas que no funcionar como se espera en el camino Amaila Falls.
A principios de este año, el gobierno rescindió el contrato inicial tenía que custodian Synergy después de que hubiera incumplido los términos de un acuerdo de terminación. Posteriormente, el proyecto fue dividido en lotes y re-licitado. Toolsie Persaud Canteras Inc., se adjudicó el contrato para construir la unión Kurupukari y también tiene el contrato para 'sección cuatro', mientras que 'la quinta sección "ha sido asignado a Ivor Allen.

El Amaila Falls proyecto hidroeléctrico está siendo vigorosamente perseguido por el Gobierno sobre la base de que reduciría significativamente EE.UU. $ 350M Guyana factura de las importaciones de combustible y minimizar el impacto del movimiento del precio del combustible en el costo de generación de energía. El desarrollo de fuentes renovables de energía es necesaria para aumentar la seguridad energética y mantener la estabilidad macroeconómica.

El proyecto, que tiene la capacidad de ofrecer más de 140 megavatios de electricidad se encuentra a orillas del río Kuribrong en Potaro, Octava Región.

En septiembre, el contrato de Ingeniería, Procura y Construcción (EPC) por valor de EE.UU. $ 506 millones en Xian, China fue firmado por Bruce Wrobel, Chief Executive Officer (CEO) de Sithe Global, y el Dr. Sun Yonggang, presidente de China Railway First Group (CRFG), para la construcción del proyecto Amaila Falls Hydro y Línea de Transmisión.


Contractors who fall short on Amaila Falls road project to be reassessed - PM Hinds

Written by   
Sunday, 02 December 2012 20:03
PRIME Minister Samuel Hinds said that a re-assessment is set to commence shortly of contractors who did not perform as expected on the Amaila Falls road.
Earlier this year, Government terminated the initial contract it had with Synergy Holdings after it failed to honour the terms of a completion agreement. Subsequently, the project was broken up into lots and re-tendered. Toolsie Persaud Quarries Inc., was awarded the contract to build the Kurupukari junction and it also holds the contract for ‘section four’, while ‘section five’ has been allocated to Ivor Allen.
    
The Amaila Falls Hydropower project is being vigorously pursued by the Government on the basis that it would significantly reduce Guyana’s US$350M fuel import bill and minimise the impact of fuel price movement on the cost of generating power.
The development of renewable energy sources is needed to increase energy security and maintain macro-economic stability.

The project which has the capacity to provide over 140 megawatts of electricity is to be located along the Kuribrong River in Potaro, Region Eight.

In September, the Engineering, Procurement and Construction agreement (EPC) valued at US$506M in Xian, China was signed by Bruce Wrobel, Chief Executive Officer (CEO) of Sithe Global, and Dr. Sun Yonggang, Chairman of China Railway First Group (CRFG), for the construction of the Amaila Falls Hydro project and Transmission Line.
Construction is expected to start in mid-2013. (GINA).

1994 Guayana Esequiba - Zona en Reclamación MARNR Servicio Autónomo  de Geografía y Cartografía Nacional 3 Edición

Nota del editor del blog: Al referenciarse a la República Cooperativa de Guyana se deben de tener en cuenta los 159.500Km2, de territorios ubicados al oeste del río Esequibo conocidos con el nombre de Guayana Esequiba o Zona en Reclamación sujetos al Acuerdo de Ginebra del 17 de febrero de 1966.

Territorios estos sobre los cuales el gobierno Venezolano en representación de la Nación venezolana se reservo sus derechos sobre los territorios de la Guayana Esequiba en su nota del 26 de mayo de 1966 al reconocerse al nuevo Estado de Guyana .
“...por lo tanto, Venezuela reconoce como territorio del nuevo Estado, el que se sitúa al este de la margen derecha del río Esequibo y reitera ante la comunidad internacional, que se reserva expresamente sus derechos de soberanía territorial sobre la zona que se encuentra en la margen izquierda del precitado río; en consecuencia, el territorio de la Guayana Esequiba sobre el cual Venezuela se reserva expresamente sus derechos soberanos, limita al Este con el nuevo Estado de Guyana, a través de la línea del río Esequibo, tomando éste desde su nacimiento hasta su desembocadura en el Océano Atlántico...”

                                                                                                  
Mapa que señala el Espacio de Soberanía Marítima Venezolana que se reserva, como Mar Territorial mediante el Decreto Presidencial No 1152 del 09 de Julio de 1968.


No hay comentarios:

Publicar un comentario